Environmental, Social and Economic Impacts of Dam Construction in Khorasan Razavi Province (Case Study of Bar Dam in Neyshabur)

Abstract:
Introduction
Any development with any quantity or quality degree has particular environmental
impacts. Human manipulation in natural environment does not necessarily mean making
changes in initial environment. Continuity of human action in the changing natural
conditions, which could eventually disrupt the balance of existing environment or
causes unintended and unforeseen consequences as currently human societies have been
facing this problem. Obviously once the idea of construction comes until the project
operation, a long and tough way must be passed over. Environmental considerations in
all phases of the project are major issues that must be considered. This includes the
entire process including design, implementation and even scheme exploitation. If
human reactions and environmental interactions are assessed in the form of construction
projects practices, environmental power and its potential will be revealed by initial
recognition. Importance and dimensions of negative effects can be achieved by using
modern methods. Based on the findings, rules can be implemented to reduce the adverse
effects and to manage the negative effects.
In recent decades, many countries, including Iran, in order to reduce problems caused
by dehydration and to prevent crisis put a massive investment in water sector.
Unfortunately, evaluations and studies conducted in the past decade on the physical
structure based on rivers and nation and international level approve existing issues and
problems in all dimensions, particularly sea water resources management or dam's water
and modern water distribution networks.
In this regard, the projects implemented and proposals examination using preliminary
studies as documentary confirms the difficulties existence in economical, ecological,
and especially social-management dimensions. In some of these projects lack of
expected goals achievement including improving beneficiaries social and economic
conditions, the relative balance between supply and demand for water resources or
agricultural prospered are effective and have caused negative reactions among beneficiaries. Present study tries to examine impacts resulted by huge investments
(physical structures) in constructing Bar-dam located in Neyshabur. Therefore, social,
economic and environmental (ecological) dimensions at the basin level of Neyshabur
bar dam in Khorasan Razavi were considered.
Since economic self-sufficiency has a particular importance, and given that the crisis of
water and dehydration is one of the major and basic public concerns, water storage and
flood water flow control are of cases that involved water engineers and experts.
Therefore, increase in water supply and flood and water flow control through the dam
construction are always recognized the fundamental measures.
Study Area :ne of the main objectives of bar dam construction is supplying part of the required rinking water of Neyshabur County. The special concentration on the Neyshabur is ecause the county is special in culture and geopolitical position. In addition, increasing ural migration to the cities and also due to the development of the town, surrounding illages are connected to Neyshabur and are using urban water distribution network and ther utilities raise more concerns on the county. The sum of these factors has led ounty to water shortage, especially in the summer. Due to the need for water supply o iroozeh (Bozghan) and Neyshabur cities and also industrial needs of Khorasan steel omplex and etc., bar dam construction and related facilities to meet these needs and ptimal use of existing potential, regional water resources have been considered as a ational and regional policies. This study attempts to answer the issues and questions or the Bar-dam. The research method in this study will be descriptive – analytical. Due o recent defects of available documents statistics, collecting data and required nformation will be carried out as documentary. Required Information of Bar dam nvironmental impacts assessment project is extracted.
Material and
Methods
garding impact assessment of development projects implementation, several methods nd procedures have been devised and used that considering intended purposes, have ifferent structures. o assess bar dam environmental impact, a Leopold two-dimensional matrix is used hich in one dimension, environment various options comes that will be affected and in ther dimension, different steps and phases of project (construction and operation) are iscussed. The virtues of this matrix are summarizing both positive and negative mpacts of the project. At this matrix first activity cases, environmental factors have een identified and the severity (impact amplitude) and the importance (magnitude) of ntended effects are considered. This matrix includes 100 small activities on the orizontal axis (columns) and 88 environmental factors on the vertical axis (rows) that esults in the formation of 8800 houses matrix or tables which every home or cell is a erge level of activity from horizontal axis and a parameter from vertical axis. fter listing sub activities and factors, when there is a possibility that one activity has n impact on environmental factor the diagonal line is drawn on soluble cell diameter as hey cross over, then in each cell two numbers are considered that one of them is omain or impact intensity and other is importance or impact magnitude. Impact mportance criteria or domain are usually valuated by ±1 to ±5. At this method mark 5 ery high and important positive impacts and mark 1 for a very low and insignificant artial effect is considered. Also grade -5 for an excessive negative effect and grade -1 or a very low negative effect is considered. Then these numbers sums and the sum of he numbers corresponding to each column represent the activity impact on all the ssessed environmental factors. Finally, for each environment (physical, economic, ocial, cultural and biological) and for each construction phase and operation of the arious options, a number is obtained, which leads to the best option. Assessing various mpacts resulting from implementing the building of engineering constructions divided o construction phase and the phase of applying in physical, biological, socio-economic, nd cultural environments in two cases of performing and failure to perform, in stages f preparing, constructing and applying, will be carried out.
Results And Discussion
Matrix generated in this study consists of 44 columns and includes factors related to the implementation and operation phases and 58 rows includes physical, biological, socioeconomic and cultural factors. After the final evaluation matrix Dam Project for two options, performing and failure to perform will be carried out. At the option seeking studies in order to determine the location of bar dam and other proposed structures in this plan several options have been considered which finally options by authorities in terms of technical and economic will be reconsidered and only one option as a best will be chosen. Therefore in bar dam environmental assessment only one option as a premier option is chosen. Therefore, in bar dam environmental assessment and related constructions, only one option is considered so performing option or failure to implement the plan is reviewed. Zero option or option Failure to implement the plan means that if dam has not been constructing in the region and the area has been abandoned, causes which environmental impact? However, for evaluating the effects of this option we should not imagine that this option will not have any deleterious effects on the region, because in some cases the lack of an implementation plan can cause a non-rectification impact in the region. Option A or option implements the plan at the current location in two constructions and operation phases is considered and the positive and negative effects of each phase have been determined. What is certain is that if implement or not implement the plan, there will be positive and negative impact on environment, but the important issue is making decision about implement or not to implement the plan. For making decision in this case, we should compare total impacts in two options of implement or failure to implement. In order to make the right decision on this issue the Leopold matrix in order to evaluate dam's construction impact on environment is used. Assessment of environmental impacts caused by dam projects in Neyshabur, Khorasan Razavi separately construction phase and operation in the physical, biological, socio-economic and cultural environments in implementing option and failure to implement option was carried out . The impact separated result shows that the total number project impact in preparation and construction phase was 398 cases, which 117 cases means 30% positive and 281 cases means 70% was negative that the main reason was different physical operation in the regional environment which often are short and required. In the exploitation phase, 123 of cases of environmental consequences was 71, means 61% positive and 49 cases means 39% was negative. Most of the adverse effects of the construction phase in implementing options are -263 which is related to physical environment and the greatest positive impact 729 is on the construction phase of implementing option on socioeconomic environment. Also negative effect in operation phase is 253 and positive effect is 473, while dam's impoundment and also considering measures related to the evaporation of water from the reservoir water level can bring desirable environmental impacts for the region and in case of water recourses reliable management cause positive impact on socio-economic development of the region. Also results show that in exploitation phase more positive impact can be seen and this is more obvious particularly in socio-economic, cultural environment. Economic environment with 729 positive points on construction phase and 384 positive points on exploitation phase has the highest positive impacts of implementing the plan.
Conclusion
Generally based on the environmental assessment performed on the bar dam project and its affiliated structures, total value of the project are 1219 points positive and 1179 points negative. The dominant aspect of the project outcomes, especially in exploitation phase is positive and in situations which consequences are negative, mostly consequences have weak and negligible destructive load which in terms of quantity can be reduced by authentic management and implementing environmental proposed measures especially implementing sand stabilization and forestry side projects in dam's construction area which can reduce project negative intensity impacts. Also, due to population growth and the increasing nutrient demands, unemployment and rural to urban migration, implementation has many positive results in employment status, income, migration, rural welfare and development of Khorasan Steel factory. So we can say that bar dam project implementation certainly has a lot of favorable impacts which trims adverse effects and creates large and significant benefits in the region. Therefore, the project is economically valuable and in order to achieve favorable objectives and keeping pace and directing with macroeconomic policy, applying an appropriate environmental management system, set activities to give direction to form the possible negative effects resulting from the implementation of such a huge project to a minimum is required.
Language:
Persian
Published:
Journal of Geography and Environmental Hazards, Volume:4 Issue: 15, 2015
Page:
127
magiran.com/p1548480  
دانلود و مطالعه متن این مقاله با یکی از روشهای زیر امکان پذیر است:
اشتراک شخصی
با عضویت و پرداخت آنلاین حق اشتراک یک‌ساله به مبلغ 1,390,000ريال می‌توانید 70 عنوان مطلب دانلود کنید!
اشتراک سازمانی
به کتابخانه دانشگاه یا محل کار خود پیشنهاد کنید تا اشتراک سازمانی این پایگاه را برای دسترسی نامحدود همه کاربران به متن مطالب تهیه نمایند!
توجه!
  • حق عضویت دریافتی صرف حمایت از نشریات عضو و نگهداری، تکمیل و توسعه مگیران می‌شود.
  • پرداخت حق اشتراک و دانلود مقالات اجازه بازنشر آن در سایر رسانه‌های چاپی و دیجیتال را به کاربر نمی‌دهد.
In order to view content subscription is required

Personal subscription
Subscribe magiran.com for 70 € euros via PayPal and download 70 articles during a year.
Organization subscription
Please contact us to subscribe your university or library for unlimited access!