Public Hospital Facilities Development Using Build-Operate-Transfer Approach: Policy Consideration for Developing Countries
Author(s):
Abstract:
Background
Advantages and limitations of build-operate-transfer (BOT) contracts in various forms of public-private partnership (PPP) arrangements have not been studied..Objectives
This study is the first of its kind to determine the framework, advantages, and limitations of BOT contracts for health care projects in selected countries..Methods
A comparative design was employed to identify factors affecting the development of medical facilities through the adoption of PPPs and the implementation of BOT contracts. England, Spain, Australia, Turkey, and Canada were selected, and data were gathered through well-known databases for the relevant studies. Electronic databases were searched using the keyword terms, build-operate-transfer, public-private partnerships, health sector/health system, health care facilities, Spain, Canada, England or United Kingdom, Turkey, and Australia..Results
The findings revealed that while there was insufficient information transparency for adoption of the BOT contract model in developing medical facilities and building new hospitals, some similarities were observed in its adoption in public fields. Adoption of the BOT contract model has been proven feasible in the selected countries for the health sector, in particular, for the development of new hospitals. These contracts are usually long-term in nature to provide the private sector with the chance to appropriately exploit the field. Different countries utilize this model to meet public regional and long-term health care needs, where the goal is not just a matter of seeking the private sectors contribution..Conclusions
This study suggests that more information transparency is required for these types of contracts. Factors such as the term of the contract, the maintenance of the facilities built and their post-completion ownership status, facilities and credits offered to the private sector during the construction and operation phases, and the provision of financial and non-financial incentives to the private sector require deeper examination and should also be adjusted to the local contexts of the developing country..Keywords:
Language:
English
Published:
Iranian Red Crescent Medical Journal, Volume:18 Issue: 12, Dec 2016
Page:
24
magiran.com/p1625581
دانلود و مطالعه متن این مقاله با یکی از روشهای زیر امکان پذیر است:
اشتراک شخصی
با عضویت و پرداخت آنلاین حق اشتراک یکساله به مبلغ 1,390,000ريال میتوانید 70 عنوان مطلب دانلود کنید!
اشتراک سازمانی
به کتابخانه دانشگاه یا محل کار خود پیشنهاد کنید تا اشتراک سازمانی این پایگاه را برای دسترسی نامحدود همه کاربران به متن مطالب تهیه نمایند!
توجه!
- حق عضویت دریافتی صرف حمایت از نشریات عضو و نگهداری، تکمیل و توسعه مگیران میشود.
- پرداخت حق اشتراک و دانلود مقالات اجازه بازنشر آن در سایر رسانههای چاپی و دیجیتال را به کاربر نمیدهد.
In order to view content subscription is required
Personal subscription
Subscribe magiran.com for 70 € euros via PayPal and download 70 articles during a year.
Organization subscription
Please contact us to subscribe your university or library for unlimited access!